You might as well know that EDSA will be extra hellish for a few days more.
“Department of Public Works and Highways (DPWH)-National Capital Region director Reynaldo Tagudando has said that the EDSA reblocking project would likely be finished by April 28,” reports Jerry E. Esplanada in the Philippine Daily Inquirer.
On Monday, April 21, it was reported that “of the remaining 27,633 square meters of road space on Edsa targeted for repairs by the Department of Public Works and Highways (DPWH) under a PHP230-million concrete reblocking program, private contractors finished working on 27,109 square meters during the Holy Week.”
Keep in mind though that they started with 85,051 square meters worth of repairs.